Denver, Colo.
January 2008 - April 2008
About the project
To help contractor Swinerton Builders access the roof system of One Lincoln Park for new construction work, the Safway Denver branch supplied cantilevered I-Beams and Systems™ Scaffold to reach most of the roof system. At 360 feet above the street, the QuikDeck™ Suspended Access System was hung from the roof to reach the 853 square feet of soffit that cantilevered 24 feet from the building. The scaffold was used by all trades to perform work on the roof system, including workers to frame the soffit and roofers to install the decorative metal finish.
Products used
Systems™ Scaffold; QuikDeck™ Suspended Access System
Services used
Engineering; Labor